ENTIRE FACILITY DIPOSAL
ENTIRE
FACILITY
DIPOSAL
Client - Leading European Manufacturing/Design Company
Client situation
Need to move out of 2 existing facilities and consolidate into one location
Need to dismantle and dispose the entire structure totalling to around 400,000 sq. ft
Need to get the bare-shell within 6 weeks of timeline to avoid penalty from the builder and with no disputes/unwanted incidents
Need to dispose to the right vendors with compliance
Need to get the right quotation
Eco eMarket Solution
Eco eMarket worked with client to define the scope of items under disposal (Client Assets, Builder Assets)
Segregation of assets into eWaste, Battery and General Waste was done
Detailed contract notes, providing clarity of assets under each segment along with the terms and conditions, were prepared
A high level project plan was worked out from inspection to restoration of building to bare shell with dependencies
A Project Manager was assigned for day-to-day activities
An Online Sealed and Online Open bid was provided for a better price realization through Pan-India buyers
Benefits
Vendor Management – Professionally executed with minimum disputes/incidents, timely hand-over to the builder with zero penalty to the client
Redirected e-waste/batteries to PCB approved buyers ensuring scientific processing – transformation from informal to formal
Guaranteed ‘Compliance’ for e-waste and battery disposal – documents for each disposal provided digitally
Price received by client was 3 times of price received from offline quotes